What it is
HSR is the US antitrust review under the Hart-Scott-Rodino Act: the parties notify the FTC and the Justice Department and wait out a set period before they may close.
Also called: HSR antitrust clearance
In plain words
Say two large supermarket chains want to merge. If the deal is big enough, they must first tell a referee and wait.
The referee checks whether shoppers would be left with too little choice. If it doesn't object in time, the wait ends.
The two can then go ahead once the deal's other conditions are met. The referee can still object later.
HSR review is that notice and that wait, for large US deals. The referees are two federal antitrust agencies.
What HSR review is for
Before many US deals can close, the companies must tell the antitrust agencies and wait.
The rule comes from the Hart-Scott-Rodino Act, so the review is called HSR. The agencies are the FTC and the Justice Department.
The wait gives them time to check whether the deal would harm competition, before the companies combine.
Say Woodgrove agrees to buy Litware for $2 billion. Both file with the agencies, and the deal can't close until the wait ends.
Which deals need a filing
Whether a deal needs a filing depends mostly on its size. The threshold is updated every year.
Since February 17, 2026, it's $133.9 million. Below that, a deal usually doesn't need a filing. A bigger one often does, depending on the companies' size and some exemptions.Source 5
The filing also has a fee. Since the same date, it runs from $35,000 to $2.46 million, rising with the deal's size.Source 5
How the wait works
The wait usually starts once both companies have filed, and lasts 30 days. In a cash tender offer, it's 15 days from the buyer's filing.
| Kind of deal | First wait | After a second request |
|---|---|---|
| Most deals | 30 days | 30 more |
| Cash tender offer | 15 days | 10 more |
These are calendar days. A wait that would end on a weekend or a federal holiday ends on the next business day.
The agencies can also end it early when the companies ask. This is called early termination.
If neither agency acts, the wait runs out. The deal is then cleared under HSR, and can close once its other closing conditions are met. The agencies can still challenge it later.
When an agency looks closer
Before the wait ends, an agency can send a second request: a demand for many more documents and data.
The deal then usually can't close until both companies have substantially complied, and 30 more days have passed. In a cash tender offer, it's 10 days after the buyer complies.Source 6
Complying often takes months. For the 16 significant US merger investigations concluded in 2025, the average from announcement to conclusion was 12.3 months.Source 7
Few deals get a second request. In the year to September 30, 2025, 41 of the 1,944 deals that could get one did: 2.1%. For deals over $10 billion, it was 21.1%.Source 6
A real example
Gilead bought CymaBay in 2024 through a cash tender offer, so the shorter wait applied.
The HSR wait expired at 11:59 p.m. Eastern time on March 8, 2024.Source 1
Gilead reported it on March 11, 2024, in an amendment to its Schedule TO. That met the offer's HSR condition.Source 1
The offer ran through March 21, 2024, and the merger closed on March 22, 2024.Source 2
How a review ends
These are the usual ways an HSR review ends. Some cases pass through more than one:
- Cleared
- The wait runs out, or an agency ends it early. The deal can close once its other conditions are met.
- Settled
- The companies agree to changes, such as selling part of a business, and the agency lets the deal go ahead.
- Challenged in court
- The agency asks a federal court to block the deal. The case can end in a ruling, a settlement or the deal being given up.
- Given up
- The companies abandon the deal, often once they learn the agency is likely to challenge it.
What it means for shareholders
A deal that needs HSR can't close before the wait ends. A second request usually pushes the expected close back by months.
If the deal closes later, the same dollar gain is spread over more time. So the annualized spread falls, even if the price doesn't move.
If a court blocks the deal, the companies often end the agreement, and the deal breaks. The review itself asks nothing of holders.
On Tracking Alpha
Tracking Alpha's deal list and deal pages aren't open to the public yet. Once they open, they'll work as described here.
HSR's stages on the deal page:
- Not filed
- The parties haven't filed yet.
- Filed
- Filed, and the waiting period is running.
- Second request
- The agencies asked for more information.
- Challenged
- The FTC or the Justice Department sued to block the deal, or said it will.
- Cleared
- The waiting period expired or was ended early.
- Failed
- A court blocked the deal, or the parties gave it up because of the review.
- Not required
- The filings say no HSR filing is needed.
On the list, the Regulatory column shows HSR when it leads the row, such as HSR wait ends Oct 16. While HSR is pending, it's also under Still needed. The HSR filter picks deals by where their HSR stands.
Point at the Regulatory column, or focus it, for the regulatory card. It gives HSR's stage in words, such as Waiting period, ends Oct 16, and the date's type. It adds a line on what the stage is when its name doesn't say, and the filing it comes from, which opens its quote.
Sometimes the wait's end passes before any filing says what happened. Then the column reads HSR wait ended Oct 2, no result, and the card Waiting period ended Oct 2, no result filed.
The dots stop short of cleared until a filing says so. When the filings give no stage, the dots are dashed.
The regulatory card draws each approval as three dots, filed, under review, cleared, beside its stage in words:
- Not filed yet
- Filed
- Waiting period, or a review under way
- Cleared
- Pending, the filings give no stage
- The date passed; no filing yet says what happened
Easily confused with
- Second request
- A demand for more information that extends the HSR wait. Only some deals get one.
- CFIUS
- A separate review of foreign buyers for national security, not competition.
Questions
Can the HSR wait be started again?
Yes, once, under HSR rule 803.12. Before the wait ends and before any second request, the buyer can withdraw its filing and refile within two business days. If the deal is unchanged and the papers are updated, that starts a new wait with no new fee.Source 3
Is HSR the only antitrust review a deal can face?
No. HSR is the US federal review. State attorneys general can look at a deal too, and so can regulators abroad, such as the European Commission.
Is an HSR filing public?
No. Under section 7A(h) of the law, what the companies file is generally kept confidential, with exceptions such as court cases. The companies often give the dates themselves, in the proxy, the Offer to Purchase or a later update.Source 4
Do deals between foreign companies need an HSR filing?
They can. It depends on the deal's value, the companies' size, and sales or assets in the United States. Being foreign can bring an exemption, so some foreign deals need no filing.
Sources
- 1Company filing: Gilead Sciences and Pacific Merger Sub, Amendment No. 2 to the Schedule TO for CymaBay Therapeutics (SC TO-T/A, March 11, 2024) (opens in a new tab)
- 2Company filing: CymaBay Therapeutics, Form 8-K on the completion of Gilead's tender offer and merger (March 22, 2024) (opens in a new tab)
- 3Law or rule: 16 CFR 803.12, Withdrawal of notification, Cornell Legal Information Institute (opens in a new tab)
- 4Law or rule: 15 U.S.C. 18a, Premerger notification and waiting period (Clayton Act Section 7A), Cornell Legal Information Institute (opens in a new tab)
- 5Regulator: Federal Trade Commission, Revised Jurisdictional Thresholds for Section 7A of the Clayton Act, Federal Register document 2026-00877 (January 16, 2026) (opens in a new tab)
- 6Regulator: Federal Trade Commission and US Department of Justice, Hart-Scott-Rodino Annual Report, Fiscal Year 2025 (2026) (opens in a new tab)
- 7Study or report: Dechert, DAMITT 2025 review: merger investigations neared record lows and remedy policies shifted (January 2026) (opens in a new tab)
Related terms
- Second requestAn antitrust request that extends the HSR wait.
- HSR waiting period endsThe day the HSR waiting period expires.
- Regulatory columnA deal's approvals summed up in one status.
- Closing conditionsWhat must happen before the deal can close.
- Tender offerA bid to buy shares straight from holders.
- CFIUSSecurity review of foreign stakes in US firms.
- European CommissionThe EU's merger review for large enough deals.
- Deal breakA deal that's terminated before it closes.
Tracking AlphaBy Jera Value · Reviewed
Was this page useful?Thanks for telling us.